CLUSTER-BASED PRIORITY LIST GENERATION FOR RESOURCE- CONSTRAINED PROJECT SCHEDULING PROBLEMS

Citations

WEB OF SCIENCE

2
Citations

SCOPUS

4

초록

Constructive Heuristics for the Resource Constraint Project Scheduling Problems (RCPSP) are preferred scheduling methods when the project network broadens. Then, to generate a good schedule from these heuristics, the priority list used in the algorithm becomes crucial. This paper proposes a Cluster-Based Priority List (CB-PL) method for generating lists to improve makespans of schedules obtained from constructive heuristics. The method creates more intellectual priority lists that generate lower makespans. The approach is built and fine-tuned upon the existing relative literature. The performance of the method is measured by comparing the makespan results. The experiment for the comparison uses serial and parallel scheduling schemes with seven priority rules. Then the experiment is tested through a set of benchmark data. Finally, schedules obtained through the CB-PL showed significant makespan reductions and increases in an overall number of better solutions.

키워드

RCPSPClusteringProject networkPriority listHeuristicCLASSIFICATIONHEURISTICSALGORITHM
제목
CLUSTER-BASED PRIORITY LIST GENERATION FOR RESOURCE- CONSTRAINED PROJECT SCHEDULING PROBLEMS
저자
Ozturk, Ahmet MelikLee, Chulung
DOI
10.23055/ijietap.2022.29.2.7957
발행일
2022
유형
Article
저널명
International Journal of Industrial Engineering : Theory Applications and Practice
29
2
페이지
154 ~ 173