석면해체공사의 적정 단가 산정Making Formular to calculate Reasonable Unit Cost for Asbestos Removal
- Other Titles
- Making Formular to calculate Reasonable Unit Cost for Asbestos Removal
- Authors
- 손기상; 갈원모; 박종태
- Issue Date
- 2011
- Publisher
- 대한안전경영과학회
- Keywords
- Asbestos Removal; Reasonable Unit Cost; Asbestos Removal; Reasonable Unit Cost
- Citation
- 대한안전경영과학회지, v.13, no.3, pp.55 - 61
- Indexed
- KCI
- Journal Title
- 대한안전경영과학회지
- Volume
- 13
- Number
- 3
- Start Page
- 55
- End Page
- 61
- URI
- https://scholar.korea.ac.kr/handle/2021.sw.korea/113721
- ISSN
- 1229-6783
- Abstract
- Unit cost for asbestos removal work which have been made out at government contract award for recent three years has been reviewed and shown with table. And the cost have been compared with ones made out by two agencies, American asbestos removal specialists, government ministry for making out comparison tables. First, legal and practical work status survey have been made to determine reasonability of introducing separate contract-awarding system, as a part of ensuring reasonable unit work cost. And then, two different status have been compared and there in introduction possibility of separate contract-awarding system, it is found out. In interior removal work case, it is thought that 50% by owner, 60% unit work cost by the expert of which removal specialist think as reasonable unit cost. The results for exterior and spray work method are shown with almost same context. Impact factors for determining unit work cost such as project amount, project kind,contract-awarding method, subcontract method have been compared with parties. Removal specialist and expert group have almost same ideas for project amount which has been hightestly weighed but owner's recognition has partially lower than specialists idea. There are almost no difference of recognition between three(3) parties for project kind. Idea comparison of reasonable unit work cost for asbestos removal work between three concerned parties has been analyzed and found out that expert group do unit work cost, 65% of which removal specialists estimate, in interior tex removal. And there is almost no difference between them in exterior roof slate removal.
But there is considerable difference between them that owner estimates 50% unit cost of specialist one while expert group estimates 60% of specialist idea of unit removal cost.
- Files in This Item
- There are no files associated with this item.
- Appears in
Collections - College of Medicine > Department of Medical Science > 1. Journal Articles
Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.